BIM-based quantity takeoff for interior fit-out
From price per unit area to a reliable quantity
A tender without quantities
An office tower in North Rhine-Westphalia, with over 43,000 m² of leasable space. Several upper floors are being refurbished; the tender is for the interior fit-out.
| Starting point | |
|---|---|
| Documentation | functional specification, 2D DWG files, PDFs |
| Quantities | none, to be determined by the general contractor |
| Main works | active metal chilled ceiling |
How the price of a chilled ceiling is determined
This ceiling cannot be estimated based on floor area alone. Almost every panel is cut differently, due to sprinklers, smoke detectors and columns. And the factory has to set up every non-standard panel individually.
It is these set-ups that drive the price, not the square meters. The cost can only be calculated from the number of variants.
From 2D plans to a classified model
OPTIMUSE converted the existing 2D documentation into a BIM model in Archicad, focusing on the ceiling panels across three floors. The basis for this was the 2D plans and the functional specification.
Every panel classified individually
Each individual panel was then classified using a semi-automated process:
- by status (new, existing, to be replaced)
- by geometry, accurate to the millimeter
- by cut-outs
Only this reveals which panels are truly identical.
The result
Result 1: 2,932 panels across three floors, recorded individually
| Status | Panels |
|---|---|
| New | Panels1,050 |
| Existing | Panels1,846 |
| To be replaced | Panels36 |
| Total (three floors) | Panels2,932 |
Result 2: 520 distinct variants instead of 929 panels
On the main floor, the analysis went into greater detail:
| Main floor | Count |
|---|---|
| Panels | Count929 |
| of which distinct variants Price basis | Count520 |
| of which with column cut-outs | Count52 |
It is not the 929 panels that determine the price, but these 520 distinct variants.
Result 3: A data set suitable for costing in less than three days
A usable data set was delivered:
- Excel lists for each floor
- a unique element ID for each panel
- IFC and Archicad files on the project platform
Less than three days after the commission was awarded. The automated analysis replaced around 12 person-days of manual quantity takeoff and delivered the figures within the tender deadline.
What this means for the tender
The tender is therefore based on a verifiable figure rather than a rough estimate. This provides protection in both directions: against under-quoting, which leads to a loss, and against over-quoting, which costs the contract.
The ceiling supplier confirmed that the data was fully usable. And the model remains usable, can be updated for further planning and can be applied to similar inquiries.